

Microgrids
This hypothetical case study will be particularly relevant to microgrid operators, local governments, community groups, universities, embedded network operators, developers, strata owners’ corporations, owners of commercial precincts or shopping centres, and other innovators looking for opportunities in this space.
There is no definition of a ‘microgrid
The regulatory regime applicable to a microgrid
Microgrid
|
Applicable regulatory framework |
---|---|
Stand-alone microgrid – led by local distributor1 |
|
Stand-alone microgrid – led by parties other than the local distributor |
|
Embedded microgrid – led by parties other than the local distributor2 |
|
State and territory regimes for microgrids - in particular, stand-alone microgrids - differ widely, including in relation to their application of energy consumer protections. For example, while most microgrid customers are limited in their choice of retailer and/or microgrid operator, many jurisdictions apply some pricing protections to these customers.
In addition, many jurisdictions have licensing and exemption regimes which enable the relevant state or territory regulator to apply certain regulatory obligations to licensees and exempt parties. Again, while the extent of these obligations can vary significantly between jurisdictions, parties wishing to sell, supply or generate electricity within a microgrid will generally be required to comply with some degree of energy-sector regulation.
This case study explores two scenarios
To help identify and unpack some of the key regulatory issues that a proponent of a microgrid
- Scenario 1 | Stand-alone community microgrid led by a party other than the local distribution business
- Scenario 2 | Under update - coming soon.
For each scenario, the following information is provided:
- a high-level overview of a hypothetical project including the project goals, project facts and ownership and service delivery models
- relevant authorisation, registration and licence requirements applicable to the hypothetical business model
- key energy specific regulatory obligations applicable to the hypothetical business model, and
- potential challenges the hypothetical Proponents may need to navigate when developing each of these business models.
The Use Cases on this website (‘Material’), are made available for use on the following basis:
- Purpose: The Material is provided for general information only. It is designed to assist you to gain a basic understanding of the subject matter and is not intended to be comprehensive. You are not permitted to commercialise it or any information contained in it. The Material is not and should not be regarded as legal, business or other professional advice. It should not be relied on and is not a substitute for obtaining independent legal, business or other professional advice relevant to your particular circumstances.
- Currency: The Material is based on publicly available information as at the date of its preparation. The Material is current as at 3 December 2021.
- Scope: The Material only covers energy market regulatory obligations that are administered by the Australian Energy Regulator (AER), the Australian Energy Market Operator or the relevant state or territory energy regulator. It does not cover other obligations that may apply, such as safety obligations, general consumer law obligations or obligations under the financial services regulatory framework. It also does not cover associated technical matters such as compliance with Australian standards or connection requirements.
- No reliance or warranty: The Material may be subsequently amended or updated. While reasonable care is taken in the preparation of the Material, the AER makes no representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of the Material, or as to its suitability for any purpose. In all cases, anyone proposing to rely on or use the Material should independently verify its accuracy, completeness, reliability and suitability for their own purposes, and obtain independent and specific advice from appropriate experts.
- Limitation of liability: To the maximum extent permitted by law, the AER and its officers, employees, consultants, contractors, and other contributors to the Material (or their respective associated companies, businesses, partners, directors, officers or employees) are not liable for any errors, omissions, defects or misrepresentations in the Material, or for any loss or damage suffered by persons who use or rely on such information (including by reason of negligent act, omission, misstatement or otherwise). If any law prohibits the exclusion of such liability, the AER’s liability is limited, at the AER’s option, to the re-supply of the information, provided that this limitation is permitted by law and is fair and reasonable.
Scenario 1 : Standalone Community Grid
Project overview
A small, isolated coastal community located in Far North Queensland is aiming to establish a self-reliant and 100 percent renewable energy supply system.
The community has a population of 1,500.
Currently, residents and businesses largely rely on importing diesel to power several generation sets. These systems are expensive to run and unreliable for the 600 residential and business premises located within the area. Some residents have solar PV
The local council, with support of the community and a locally owned renewable energy company (the ‘Proponent’) are developing an alternative supply solution for the area. In partnership with several technology vendors, the Proponent plans to utilise innovative energy technologies to coordinate wind generation, residential solar PV, a battery energy storage system
Infrastructure to enable EV charging stations will also be incorporated into the microgrid
Project goals
The isolated community microgrid project seeks to:
- increase reliability of electricity supply
- reduce electricity costs for the community (largely driven by diesel generation and accounting for currently 20-30 percent of average household income), and
- power the community from 100 percent renewable generation.
Project facts
Stand-alone community microgrid |
|
---|---|
Location |
Far North Queensland |
Population |
1,500 |
Households and businesses |
600 |
Proponent |
A locally owned renewable energy company in partnership with the local council |
Microgrid
|
|
Combination of wind, solar and battery storage, plus diesel generation for back-up |
10MW |
Ownership and service delivery
Through a cost-sharing arrangement, the Proponent plans to implement a community-ownership model which will give the community (individuals, households and businesses) the option to take partial ownership of the key local energy assets – that is, the wind turbines and battery energy storage system
Given the size of the microgrid
- local generation and energy storage services (electricity for supply and sale within the microgrid)
- network services (supply of electricity within the microgrid)
- retail services (sale of electricity within the microgrid), and
- supporting services, such as metering.
Using smart technologies developed in partnership with an innovative technology firm, the Proponent also plans to perform activities related to system operation, including system control, installation, operation and management of the remote electricity supply.
Overview of authorisation, registration and licensing requirements
The National Energy Retail Law
The National Electricity Law
In Queensland,5 anyone intending to operate electricity infrastructure needs to hold an electricity licence (‘electricity authority’).6 Specifically, generators need a generation authority (unless the generating plant they operate has a capacity of 30MW or less), and network service providers need either a transmission or distribution authority.
Alternatively, a ‘special approval’ could be sought from the Queensland Department of Energy and Public Works which would enable a party to perform the activities of a generator
The licensing requirements (or exemptions) that are potentially applicable to this case study include:
- Queensland generation authority (or deemed special approval) - Given the Proponent will operate generating plant with a capacity of less than 30MW, it will be eligible for a deemed special approval allowing it to connect generation to the microgrid
Any system supplying multiple customers not physically connected to the grid. Includes anything from a large town to two farms connected to each other. Generation sources typically include solar PV, wind turbines and small-scale gas generators and diesel engines. Alternatively, microgrids are electricity networks that can be isolated and operated independently of the interconnected electricity system (or “grid”).without requiring a generation authority.
- Queensland distribution authority (or special approval) - As the owner/operator of the supply network within the microgrid, the proponent would need to obtain a distribution authority containing certain conditions.
Description of key energy specific regulatory obligations
The table below sets out the key regulatory obligations that may be applicable to the Proponent as a result of the various registrations, authorisations and jurisdictional licenses that apply.
Requirement |
Key regulatory obligations |
---|---|
Authorisations and exemptions |
|
Retailer authorisation required |
Authorised retailers must comply with the National Energy Retail Law
Authorised retailers have various obligations in respect of the sale and supply of electricity to small customers, relating to:
|
Licences and exemptions – |
|
Exempt from requirement to hold a generation authority (deemed special approval) |
A generation entity acting under a special approval must comply with relevant provisions set out in the Electricity Act 1994 (Qld) including:
|
Distribution authority required7 |
A distribution authority is subject to a set of conditions set out in the Electricity Act 1994 (Qld) requiring (among other things):
It must also comply with additional conditions set out in the Act, including in relation to:
|
Other energy specific regulatory obligations
In addition to the regulatory obligations that flow from the various registration, authorisation and jurisdictional licensing requirements, the Proponent will also need to be aware of other energy specific regulatory obligations under the national and relevant jurisdictional energy frameworks. For example:
Safety provisions set out in the Electrical Safety Act 2002 (Qld) cover microgrid
Other than in South East Queensland where electricity prices have been deregulated since 1 July 2016, retail electricity prices in Queensland are regulated by the Queensland Competition Authority. The uniform tariff policy means that the prices applicable to residential customers supplied by in a microgrid
The Queensland Electricity Distribution Network
If the Proponent is considered a ‘retailer’ they will need to be a scheme participant under the Queensland Energy and Water Ombudsman Act (2006).
The Australian Energy Market Commission
Potential challenges for this hypothetical Proponent and their business model
The above discussion frames the breadth of regulatory obligations that the Proponent could face for the hypothetical project considered in this scenario.
In this context, there are a series of threshold questions that a proponent considering this, or a similar, business model may wish to consider in the early stages of their project.
The microgrid
Transitioning customers to a new model of supply will involve the transfer, removal or decommissioning of the set of assets previously used to supply the customers of the microgrid
Retail electricity prices are subject to some form of regulation in all states and territories, either under the Default Market Offer (DMO) or under jurisdictional price regulation. In some states and territories, those price caps also apply to microgrids, while in other jurisdictions they only apply to customers connected to the National Electricity Market
Scenario 2 : Under update, coming soon.
Additional information
Ongoing reforms and policy development
Other information
1Distribution businesses are permitted to provide standalone power systems to existing customers as an efficient alternative to upgrading or replacing an existing network connection.
2Embedded microgrids are private electricity networks connected to another distribution or transmission system through a parent connection point.
3As explained in the AER (Retail) Exempt Selling Guideline, exemptions were developed to manage the practice of ‘on-selling’ energy – that the main relationship the on-seller has with their customer is not the sale of energy. Most (but not all) exemptions are held by on-sellers.
4Certain provisions of the NER could apply to standalone microgrids if a jurisdiction chooses to list a party as a ‘nominated distributor’ in the relevant regulation. In this case, the nominated distributor may be required to comply with certain provisions set out in the Rules relating to connection services, retail support obligations and credit support obligations, including in Chapter 5A (Electricity connection for retail customers).
5See: Electricity Act 1994 (QLD).
6These provisions apply to generators, transmission entities and distributors whether they are connected to the national grid or not.
7In this hypothetical case study, the Proponent chooses to seek a distribution authority. Alternatively, the Proponent could have chosen to seek a special approval which is also subject to a set of conditions set out in the Electricity Act 1994 (Qld).
8These service levels would not apply to microgrids operated under special approvals unless the special approval contains a condition requiring compliance with the Code.
9See: https://www.aemc.gov.au/sites/default/files/2019-10/AEMC%20SAPS%20prior….
10Registration fees are set out in AEMO’s electricity market fees schedule. See: https://aemo.com.au/about/corporate-governance/energy-market-fees-and-c…
12The “registerable” exemption categories applicable to the sale and distribution of electricity are relevant where there are more than 10 residential or business customers within an embedded network
13Other forms of exempt sellers also face a regulated price cap which is set at the local area retailer’s standing offer prices in place on or immediately prior to 27 May 2019. This applies to embedded network customers with annual consumption >40MWh, construction sites taking temporary supply, customers of exempt sellers who are related parties, customers of exempt sellers in conjunction with telecommunications services, exempt multiple activity providers.
14Provisions of the EDC that apply to exempt entities include those related to quality of supply (other than in respect of frequency and voltage), connection of supply (other in respect of equipment and new connections), emergency response plans and disconnection of supply.